Expo 2020 Dubai: Crowning of Al Wasl Dome

  • Al Wasl Dome will be the Al Wasl is the central piece of Expo 2020 Dubai
  • Over 800 engineers and technicians help build the dome
  • Massive Al Wasl dome structure complete after intricate, complex engineering feat
  • Precision raising of 800+ tonnes of steel had a margin of error of three millimetres

Months of planning have successfully led to the final piece of Al Wasl dome being lifted into place after an intricate and complex construction operation. The dome’s huge steel crown was positioned at the top of the jewel of the Expo 2020 Dubai site in an inspiring feat of precision engineering.

Enclosing a space of 724,000 cubic metres and standing 67.5 metres tall – higher than the Leaning Tower of Pisa – the 130-metre-wide domed steel trellis encircles Al Wasl Plaza, a structure that will be the heart of the Expo 2020 site and set to become Dubai’s latest architectural landmark.

Here’s a preview of the completion of Al Wasl Dome:

His Highness Sheikh Ahmed Bin Saeed Al Maktoum, Chairman of the Expo Dubai 2020 Higher Committee, President, Dubai Civil Aviation Authority, Chairman, Dubai Airports, Chairman and Chief Executive, Emirates Airline and Group, said: “The crowning of the Al Wasl dome is a significant landmark not just for Expo 2020 Dubai but for the whole of Dubai and the UAE. This new architectural marvel joins a long list of inspiring designs that our country has created through collaboration, sheer hard work and the unending, ambitious vision of our leadership and people. It is another example of what the nation can do when it combines all its talents to such formidable purpose.”

During Expo 2020, Al Wasl dome will be the largest 360-degree projection surface in the world, providing an unparalleled experience for millions of visitors. The crowning of the dome is a key milestone for Expo 2020, with all permanent Expo-led construction on track to be completed by the end of the year.

Al Wasl Expo 2020 Dome

Weighing 550 tonnes of moulded steel, Al Wasl dome’s 22.5-metre crown had to be precisely positioned on top of the vertical trellis, with a margin of error of only three millimetres. It was completed using a technique called strand-jacking. Including the structures and equipment required to lift the dome during this process, the total weight was 830 tonnes – equivalent to 600 saloon cars.

Eighteen hydraulic jacks, aided by steel lifting ropes connected to 18 freestanding temporary columns, were used to slowly raise the curved steel crown. It was positioned directly on top of the trellis already in place 45 metres above the ground, and attached using 53 temporary connection brackets. Working through the night, 800 engineers and construction technicians carefully monitored every millimetre of the process, using GPS indicators throughout to ensure perfect alignment.

Al Wasl Dome Expo 2020 dubai

Ahmed Al Khatib said: “Crowning Al Wasl Dome was both incredibly exciting and one of the most challenging engineering operations in the world. Lifting such a large and heavy structure involved a huge number of variables. Something as simple as a shift in direction of the wind or change in air temperature could have had a big impact on our calculations, so constant monitoring and reassessment was essential throughout the process.”

The name Al Wasl means ‘connection’ in Arabic, and Al Wasl Plaza will be the beating heart of the Expo 2020 site, connecting the three Thematic Districts and providing a focal point for visitors throughout the six-month event. Al Wasl Plaza has been designed to form a grand ‘urban room’, a meeting place that creates a shaded microclimate unlike anywhere else in Dubai; a space that simultaneously and uniquely encompasses vibrant performances and natural landscaping.

Reflecting the theme of Expo 2020 Dubai, ‘Connecting Minds, Creating the Future’, the design and construction of Al Wasl dome is a global collaboration, involving contributions from companies from 13 countries.

Al Wasl Plaza, which includes the dome’s unique and iconic structure, was designed by US-based architects Adrian Smith + Gordon Gill Architecture; the raw steel for the trellis was sourced from the Czech Republic, Hungary and Poland; the steel was shaped into its flowing curves by companies in Belgium, Germany and Spain, before being moulded into its intricate latticing in Italy by Cimolai Rimond. The steel trellis was shipped in batches to Dubai by DP World, Expo 2020’s Premier Global Trade Partner. Expo 2020’s Official Programme Delivery Management Provider, Jacobs Mace, worked on the overall project management and companies from the United States, Canada, China, France, Japan and Mexico also played key roles in the completion of the dome.

Crowning of Al Wasl Dome Expo Dubai

Crowning of Al Wasl Dome Expo Dubai

In preparation for its pivotal role at Expo 2020, Al Wasl dome’s steel structure will next be transformed into an immersive 360-degree projection surface, with projections visible both from within the dome, providing a unique visitor experience. Fitted with state-of-the-art projectors by audio-visual experts Christie, Expo 2020’s Official Projection and Display Partner, the dome will host performances from A-list global performers and other major celebrations, on key international occasions such as New Year’s Eve, Diwali and Chinese New Year.

Expo 2020 Dubai runs for six months, between 20 October 2020 and 10 April 2021 and expects to welcome 25 million visits, with 70 per cent of visitors projected to come from outside the UAE – the largest proportion of international visitors in the 168-year history of World Expos. For 173 days, it will be the World’s Greatest Show, and many of the 60-plus live events per day will be held in Al Wasl Plaza.